Who
Owners
Where
A job → More actions → Edit details → Agreed price; a job → Activity.

When a job’s agreed price changes, its Activity records the old and the new price, who changed it and the reason. Once a job has been completed, a new price needs a reason.

“Why did this job end up $300 more?” Months later, nobody remembers. The history answers it, and a price that changes after the work is done always comes with its why.

  • Changing the price: people who set prices: owners and the Estimator role.
  • The price changes in Activity: people who see prices: owners, Estimator, Accountant. Office and field workers don’t see these entries.
  1. A completed job is locked. To change its price, click Reopen first.
    A completed job, locked, with the Reopen button outlinedA completed job, locked, with the Reopen button outlined
  2. Open More actions (⋯) and choose Edit details. Type the new Agreed price, and in Reason for a price change say why. Click Save changes.
    Edit job: agreed price $2,150.00 and the reason: two more flood lights on the garage, asked for on siteEdit job: agreed price $2,150.00 and the reason: two more flood lights on the garage, asked for on site
  3. Scroll to Activity. The entry shows who changed the price, the reason, and the old and new price.
    Activity: Mike Carter changed the agreed price, with the reason and $1,850.00 → $2,150.00Activity: Mike Carter changed the agreed price, with the reason and $1,850.00 → $2,150.00
  • On a job that has never been completed, the reason is optional; the change is recorded either way, with the old and new price. Once a job has been completed (even if it’s open again now), Skuadro won’t save a new price without a reason.
  • An approved change order raises the price too, and records it the same way, with the change order as the reason.
  • The history can’t be edited or deleted.
  • A reason can be up to 200 characters.